COVERT, MI – The effort to restart the Palisades Nuclear Generating Station is entering its most consequential regulatory phase, as missing decades-old weld documentation forces owner Holtec International to seek relief from federal regulators.
At issue is whether the 800-megawatt nuclear plant — shut down in May 2022 after 51 years of operation — can safely return to service without complete certified material test reports tied to safety-critical reactor welds.
Holtec has acknowledged in public meetings with the U.S. Nuclear Regulatory Commission that certain original fabrication records cannot be located. Rather than replacing the components, the company is preparing to request “regulatory relief,” allowing it to demonstrate safety using alternative engineering analysis and surrogate data.
That request now sits at the center of the restart debate.
$1.52 Billion in Federal Backing
The financial stakes are substantial.
In September 2024, the U.S. Department of Energy’s Loan Programs Office closed a conditional loan guarantee of up to $1.52 billion to support Holtec’s effort to restore and resume operations at Palisades. Hundreds of millions of dollars have already been disbursed toward inspections, equipment upgrades and workforce rehiring.
The State of Michigan has also approved additional economic development incentives tied to the restart.
Supporters argue the plant’s return would provide 800 megawatts of carbon-free baseload electricity — enough to power roughly 800,000 homes — strengthening grid reliability as coal plants retire and renewable capacity expands.
Opponents counter that public dollars should not underwrite elevated technical risk at an aging facility missing key records.
The Weld Documentation Problem
The documentation issue involves welds connected to reactor pressure boundary components — areas responsible for containing high-temperature, high-pressure coolant inside the reactor system.
Under federal nuclear regulations and American Society of Mechanical Engineers standards, certified material test reports verify metallurgy, fabrication procedures and inspection compliance.
Without those records, regulators must determine whether engineering modeling and comparable material analysis can provide what the NRC calls “reasonable assurance of safety.”
Holtec maintains that any relief request will undergo full NRC review and that the restart will not proceed without regulatory approval.
Supporters point to a recent NRC environmental assessment that found “no significant impact” from the restart, a milestone proponents argue demonstrates the project remains within federal safety frameworks.
In addition, emergency preparedness officials from FEMA and state agencies have publicly discussed coordination efforts tied to a potential reopening, emphasizing readiness and oversight.
Palisades Restart: What’s at Stake
Plant Capacity: 800 megawatts (enough for ~800,000 homes)
Federal Support: Up to $1.52 billion DOE loan guarantee
-
- Original Restart Target: Late 2025
Current Timeline: Early 2026 (subject to NRC review)
Key Issue: Missing certified weld documentation
Regulatory Action: Holtec preparing request for NRC “regulatory relief”





